T-7A Recapitalization
Environmental Impact Statement
Columbus Air Force Base, Mississippi
Documents related to the Environmental Impact Statement (EIS) for T-7A Recapitalization at Columbus Air Force Base (AFB) are available here for downloading or online browsing.
The following materials were developed as part of the public scoping process. The public scoping period ended on May 2, 2022.
The Draft EIS for T-7A Recapitalization at Columbus AFB can be downloaded from the links below.
Executive Summary of the Draft EIS
File 1: Executive Summary. This file is the executive summary of the Draft EIS. This file is approximately 2 megabytes.
Draft EIS
File 2: Draft EIS. This file is the Draft EIS and appendices. It contains the description of the Proposed Action and alternatives, affected environment, and environmental consequences. This file is approximately 25 megabytes.
Supporting Materials for the Draft EIS
File 3: Detailed ACAM Reports. This file contains additional air quality analysis supporting documentation, including the detailed Air Conformity Applicability Model reports containing the air emission calculations. This file is approximately 17 megabytes.
A Notice of Availability for the Draft EIS was published in the Federal Register on October 6, 2023. Notice of Availability
A Notice of Availability for the Draft EIS and notice of the public hearings was published in The Dispatch and Starkville Daily News on October 7 and 20, 2023. Newspaper Notice of Availability
The slide show for the October 25 and October 30, 2023 public hearings. Project Presentation
The posters shown at the October 25, 2023 in-person public hearing.
An informational brochure about T-7A recapitalization. Informational Brochure
The Final EIS for T-7A Recapitalization at Columbus AFB can be downloaded from the links below.
Executive Summary of the Final EIS
File 1: Executive Summary. This file is the executive summary of the Final EIS. This file is approximately 2 megabytes.
Final EIS
File 2: Final EIS W/O Appendices. This file is the body of the Final EIS. It contains the description of the Proposed Action and alternatives, affected environment, environmental consequences, and responses to the comments received for the Draft EIS. The appendices of the Final EIS have been removed from this file and moved into a separate file to improve download time. This file is approximately 40 megabytes.
File 3: Final EIS Appendices. This file contains the appendices of the Final EIS. The appendices are:
This file is approximately 50 megabytes.
Supporting Materials for the Final EIS
File 4: Detailed ACAM Reports. This file contains additional air quality analysis supporting documentation, including the detailed Air Conformity Applicability Model reports containing the air emission calculations. This file is approximately 17 megabytes.
A Notice of Availability for the Final EIS was published in the Federal Register on May 3, 2024. Notice of Availability
A Notice of Availability for the Final EIS was published in The Dispatch and Starkville Daily News on May 3 and 4, 2024. Newspaper Notice of Availability
The Record of Decision was signed on August 19, 2024.
A Notice of Availability for the ROD was published in the Federal Register on August 27, 2024. Notice of Availability
A Notice of Availability for the ROD will be published in The Dispatch and Starkville Daily News on August 30 and 31, 2024. Newspaper Notice of Availability